August 6, 2002 Long Island needs more reasonably priced
electricity. Where will it come from? According to a new study by
the Center for Management Analysis at the C.W. Post Campus of Long
Island University, the modernization and re-powering of the Islands
existing power stations will forestall the need for new generating
sites for 20 to 40 years and beyond.
The study concludes that the age of the existing facilities is
not a drawback. The report states that although these plants are
not brand new, they "are excellent candidates for conversion
to state-of-the-art combined cycle technology. For each unit converted,
the generating capacity would essentially triple and the operating
efficiency would nearly double." The first of such conversions
could be finished by 2006.
Finding more energy for Long Island ultimately means re-powering
some facilities with newer, more efficient technology. This could
mean abandoning existing oil/gas fired boilers, while installing
new combustion turbines and waste heat recovery boilers in their
place. These combined cycle conversions, according to the study,
achieve higher efficiency by using the exhaust gas from the systems
combustion turbine to make steam that powers an additional generator.
Combined cycle technology is already used on Long Island in the
New York Power Authoritys Flynn Plant in Holtsville and the
Trigen-Nassau Energy Corp. plant in Mitchell Field.
"If all of the existing steam electric plants were converted
to combined cycle, Long Islands electric supply could potentially
be increased by about 4,700 megawatts (MW)," said Dr. Matthew
C. Cordaro, director of the Center for Management Analysis. This
technology could also be used to convert the simple cycle 240MW
combustion turbine plant at the Shoreham Nuclear Plant site, offering
120 MW of additional energy with greater efficiency.
Another benefit of re-powering lies in the environmental benefits.
Converting to combined cycle almost doubles operating efficiency,
reducing the amount of natural gas or fuel oil required to produce
electricity. It also results in reduced emissions into the air and
allows the continued use of existing cooling systems. Furthermore,
re-powering costs $200 to $400 less per KW than building plants
at so-called "greenfield sites" brand new, previously
undeveloped sites and two to three times less than building
and relying on alternate forms of energy generation.
The study also recommends that proposed power projects now in the
New York State licensing process be completed to accommodate the
growth in electric demand on Long Island while existing plants are
being upgraded and to serve as a back-up for outages that may be
necessary at existing plants during the re-powering process. Finally,
the study observes that re-powering does not necessarily preclude
the potential for competition in electric supply to be introduced
to Long Island. LIPA still has the option of purchasing at least
some of the existing KeySpan plants within three years and could
resell these facilities to competitive generating companies perhaps
through an auction.
The Center for Management Analysis (CMA) is an academically based
organization that serves the diverse needs of government, business
and the community by focusing on energy, environmental management
and economic development issues. Its purpose is to provide a climate
for research, consultation and problem solving by uniting educators
and practitioners in addressing public issues. The Centers
director, Matthew C. Cordaro, Ph.D., a 35-year veteran of the energy
industry, has extensive management and administrative experience
in all sectors of the energy business.
For additional information or a copy of "The Feasibility of
Re-powering KeySpans Long Island Electric Generating Plants
to Meet Future Energy Needs," please call Dr. Cordaro at (516)
299-3920 or email mcsqd22@aol.com.
|